Overhead absorption is a systematic process of distributing overhead among the units produced. That overhead has already been allocated, apportioned, and reapportioned to production departments.
Overhead Absorption Rate
The rate at which overheads are charged to the cost units. Computed as either an actual rate or a predetermined rate.
Absorbing production overheads ensures the full production cost of a product is known. Actual overheads and activity levels are only known at the end of the period. Predetermined or budgeted figures are used instead.
Basis is the units, cost, or hours used as the denominator.
Predetermined OAR
Used for planning, control, and pricing purposes.
Actual OAR
Methods of Overhead Absorption
Production Unit Method
Percentage Methods
Where the base is one of:
- Direct labour cost.
- Direct material cost.
- Prime cost.
Hourly Rate Methods
Where hours is one of:
- Direct labour hours.
- Machine hours.
Blanket Overhead Absorption
Total production overheads of the organization are absorbed on a single absorption basis, giving only one rate for the entire unit, plant, or department. Simple to apply.
Inaccurate when departments differ in the overhead they incur. A single rate does not reflect how each department’s output actually consumes overhead.
A separate rate per department gives more accurate product costs in that case. Each rate is based on whichever resource that department’s process consumes most. For example, machine hours for a machine-intensive department, labour hours for a labour-intensive department.
Absorbed Overhead
The overhead charged to production using the absorption rate, computed as the absorption rate multiplied by the actual activity level.
Comparing it against the actual overhead incurred gives under-absorption (absorbed overhead less than actual) or over-absorption (absorbed overhead more than actual). Arises for 1 of the following reasons:
- Actual overhead costs differ from budgeted overheads.
- The activity level differs from the budgeted activity level.
- Both actual overhead and activity level differ from budget.
Worked Example
Budgeted production overhead for the period is , budgeted output is units, budgeted direct labour hours are , budgeted direct labour cost is , and budgeted direct material cost is .
Production cost per unit, using the OAR from the Production Unit Method:
By the end of the period, actual output is units and actual overhead incurred is . Using the predetermined OAR from the Production Unit Method:
Since absorbed overhead () is less than the actual overhead incurred (), there is under-absorption of .
Selling price per unit is and units sold for the period are .
Under-absorption is charged as an additional expense, since actual overhead incurred exceeds what was absorbed into production cost.